Project Completion & Certified Sign-Off
Overall Portfolio Progress
15%
Cap-Haïtien
ON TRACKHaiti Infrastructure Bond — Series A
23%
Phase 1 site clearing and survey complete
✓ Certified by Eng. Marie-Claude Pierre on 2026-03-15
On schedule per contract terms
Southern Peninsula
AT RISKHaiti Clean Water Bond — Series A
18%
Equipment procurement 60% complete; delivery delays from supplier
Supply chain delay — revised delivery Q3 2026
Western Region
ON TRACKHaiti Energy Bond — Series A
5%
Land acquisition and grid study complete
✓ Certified by Ing. Josué Francisque on 2026-04-01
Early phase on track
Central Plateau
ON TRACKHaiti Education Bond — Series A
31%
62 of 200 school rehabilitation sites complete
✓ Certified by Min. Éduc. Rep. Carole Auguste on 2026-02-28
Ahead of quarterly target
Artibonite Valley
OFF TRACKHaiti Agriculture & Nutrition Bond — Series A
12%
Irrigation canal preliminary work underway; eminent domain dispute in 2 zones
Legal resolution pending — at risk of Q3 delay
Grande Anse & Nippes
AT RISKHaiti Urban Development Bond — Series A
2%
Site surveys complete; permitting process initiated
Municipal approvals pending